Skip to the main column
Genset Digest Diesel power & process air

Genset Digest / International Case Studies / Sintering cooling blower

21/07/2026 International Case Studies Process air retrofit

Sintering Machine Loop Cooling Blower

Replacing a cooling blower on a sinter plant loop cooler is harder than buying a new one: the foundation, the ductwork, the noise limit and the shutdown window are all fixed before the specification starts. This profile sets out the requirements such a retrofit is normally written around.

Replacing a cooling blower on a sintering machine loop cooler is a harder brief than buying a new one, because almost nothing about the installation is open to negotiation. The foundation exists. The ductwork exists. The noise limit at the plant boundary exists and has usually tightened since the original machine was installed. And the shutdown window in which the change has to happen is measured in days.

This profile sets out the technical requirements that a retrofit of this type is normally written around. It describes a project type rather than a named engagement, because the constraint list is the part that transfers from one plant to the next.

Circular cooler at a sinter plant seen from a walkway, hot sinter on the rotating bed, cooling air ducts entering from below and steam rising from the surface
The loop cooler takes sinter off the strand at several hundred degrees and has to hand it on cool enough for the conveyors downstream.

The duty that has to be matched

A loop or circular cooler receives hot sinter from the strand, typically in the range of 600 to 800 degrees Celsius, and has to deliver it cool enough for the downstream conveyors and screens, which usually means below about 150 degrees. The air requirement follows from the heat to be removed rather than from any duct calculation, and is commonly expressed per tonne of sinter, in the region of 2,000 to 2,800 cubic metres of air per tonne.

Because the cooler is a rotating bed with a variable depth and a variable permeability, the fan does not sit at one clean duty point. It has to hold its flow across a band, which pushes the selection toward a machine with a flat pressure characteristic in the working region rather than one with the highest peak efficiency.

RequirementTypical figureWhy it is set there
Airflow2,000 to 2,800 m3 per tonne of sinterHeat removal to below 150 degrees C
Airflow toleranceWithin about 5 % of designBed depth and permeability vary
Static pressure3 to 8 kPaBed resistance plus ductwork
Noise limitCommonly 85 dB(A) at 1 mPlant hearing protection policy
Duty cycleAround 8,000 h per yearRuns whenever the strand runs
Dust in the air streamAbrasive finesBlade wear becomes the service driver

Airflow tolerance, and why it is written into the contract

A tolerance of plus or minus 5 per cent on delivered airflow sounds generous until it is tested. Site acceptance is normally by measurement in the duct, and duct measurement is not easy: it needs a straight run of adequate length upstream, a proper traverse grid, and a correction for the actual gas density on the day. Plants that omit the straight run from the layout end up unable to prove the machine either way, which is a contractual problem rather than an engineering one.

The measurement discipline here is the same one that governs the low-pressure cooling duties described in the Stelmor blower page: you verify the air, not the motor current, because current tells you what the machine is absorbing and not what the process is receiving.

Leave room to measure

A retrofit specification should name the measurement plane, the straight duct length available upstream and downstream, and the method to be used. Without those three, an airflow tolerance is an unenforceable number and the acceptance test becomes an argument about instruments.

Noise, which is usually the tightest constraint

Noise limits on plant equipment are commonly written as a sound pressure level at one metre from the machine, with 85 dB(A) a frequent figure because it aligns with hearing protection policy inside the plant. Meeting it on a large fan is rarely a matter of the fan alone. The contributors are the impeller, the motor, the inlet, the discharge and the ductwork radiating structure-borne noise, and an acoustic enclosure around the machine does nothing for a duct that sings.

The practical answer is a package: inlet and discharge silencers sized for the actual spectrum, flexible connections at both ends, and an enclosure only where the residual requires it. On a retrofit the silencers have to fit the existing duct route, which is exactly the sort of constraint that eliminates otherwise suitable machines at the survey stage.

Engineer holding a sound level meter on a tripod one metre from a running industrial fan, ear defenders on, measurement notes clipped to a folder
Acceptance at one metre: the fan is only one of the sources, and the ductwork is frequently the one that fails the test.

Foundation, envelope and the shutdown window

The existing foundation was cast for the original machine, with its bolt pattern and its mass. A replacement of a different frame size means either a new base plate that spans the old bolts or a foundation modification, and the second option consumes shutdown days that do not exist. The survey that establishes this, bolt centres, existing grout condition, available headroom for the crane, and the route the rotor will travel through the building, is the single most valuable day of the whole project.

Duty cycle closes the brief. A machine running roughly 8,000 hours a year is a continuous-duty machine, so the bearing arrangement, the lubrication method and the wear allowance on the blades all have to be specified for continuous service rather than for intermittent. The wear side of that decision is developed in the dedusting blower page, and the general sizing framework in the industrial blower section.

Exposed anchor bolts and grout pocket on a machine foundation with the old base plate lifted away, chalk marks on the concrete and a steel rule laid across the bolt centres
The survey of the existing foundation decides which machines are still candidates, and it happens before any selection.

Read next

For the sizing discipline behind this brief, including system resistance and gas density corrections, read the dedusting blower page.

For the same measurement principle applied to a low-pressure cooling duty, the Stelmor blower page covers airflow uniformity on a rod line.

The export-project constraints around a brief like this, shipping, climate and parts distance, are collected in the international case studies hub, with the domestic profiles in the case studies section.